Another mechanical issue is holding up repairs to a historic drawbridge connecting Mare Island and Vallejo, the city said Wednesday.

The Mare Island Causeway Bridge has been partially closed to traffic for over a year while crews work to upgrade the ailing structure, which was built in 1934.

Last week, the 165-foot bridge was fully closed to traffic while Vallejo Public Works crews repaired an imbalance on the structure’s east side that emerged during construction work, which started in August 2025. The repairs didn’t work, according to the city, and crews found another problem — a metal coupling that helps raise and lower the bridge for boats was broken.

Scaffolding and construction barriers are visible near the center towers of the Mare Island Causeway Bridge in a September 2026 Google Street View image. Traffic has been reduced to a single lane during ongoing repairs to the drawbridge. (Google image)

For now, the drawbridge is closed to boats and marine traffic until the coupling is replaced. As usual, the single lane on the westbound side of the bridge heading into Mare Island remains open to cars and trucks. Bike and pedestrian lanes will stay closed weekdays until Friday.

The city also issued a warning to residents that highly carcinogenic materials — polyester concrete and methyl methacrylate — will be applied to the bridge during weekdays, possibly causing nausea and headaches.

One setback after another has halted repairs, including the discovery of a rare bird species nesting near the construction site in July. Completion of repairs is now scheduled for March 2027, the city said.

According to the city, the coupling is a specialized part and could require custom fabrication to replace. Only after that can crews resume work to fix the bridge’s structural imbalance. A full closure of the bridge for those repairs will be scheduled after the metal coupling is replaced.