The Pittsburg City Council voted unanimously this week to approve a temporary moratorium on any new data center construction at a contentious meeting that had to be paused at one point amid loud chants of “no data centers!” from attendees.
The vote came Monday after months of lobbying by residents and local advocacy groups urging a total halt to the construction of a data center being built on the site of the former Delta View Golf Course, the Avaio Perseus Data Center.
The pause will apply to the project’s next construction phases but will not cover its Phase I already under way.
Multiple residents who spoke during the public comment period criticized the City Council for allowing the project to proceed with its current first phase of construction while the moratorium was in effect.
The moratorium was passed as a 45-day urgency ordinance. It can be extended for up to two years from its original passage date of Monday. Its purpose is to give city leaders time to add a definition of an artificial intelligence data center to the city’s zoning code, which would give it the ability to further regulate them. The city code does not currently define a data center, making it hard to regulate them separately than other technology infrastructure projects.
Artificial intelligence data centers house hardware components needed to process large amounts of information used to power technology that uses AI. They typically include large numbers of servers — which store, process and transmit data — and other hardware to facilitate computer networking and information transmission.
Concerns over pollution and power use
AI data centers use more energy than previous data centers and also require a cooling source, such as water, to keep equipment from overheating.
They also require constant connection to power, which means having large numbers of generators at the ready for when electric power grids go down. Pollution and sound from generators that run on diesel fuel have been one of the top concerns from communities around the nation opposing the centers.
Other places — including San Francisco, Oakland, Gilroy, and San Mateo County — have made similar moves in recent months in reaction to nationwide pushback against environmental and other impacts from AI data centers, including high energy use, water and air pollution, and noise.
Pittsburg City Councilmembers voted 4-0 to approve the moratorium, with Mayor Dionne Adams recusing herself because she serves on the Board of Directors of the Pittsburg Power Company and works for PG&E, both of which are involved in negotiations about supplying power to the data center. Those positions were deemed a conflict of interest in February by the California Fair Political Practices Commission.
As a city, we have fallen short and we need to own that.
Mayor Dionne Adams
Before she left the council chamber, Adams told a raucous crowd that the city could have done better in letting residents know about the project and could have been more transparent about the process.
“I hear your frustration, your worry for your families and neighbors, and your feelings that decisions affecting your future were made without your consent,” Adams said. “As a city, we have fallen short and we need to own that.”
She noted that the data center was first contemplated in 2018 as part of a technology park, and that the slow-moving process had made many feel blindsided when they finally became aware of it. She said the city needed to reflect on its processes for involving residents in discussions about major projects.
“Whatever outreach took place then, we must not dismiss what residents are telling us about their experience today,” she said.
‘Tell them to stop’
Many public commenters lambasted the City Council for what they said was a process that had moved the project forward with little-to-no public notice or transparency.
City Councilmember Jelani Killings disputed that accusation later at the meeting and took time to read into the meeting’s record several news articles from previous years reporting on the data center project’s consideration and approval.
The project was given its first approval under a development agreement in 2019. It had an Environmental Impact Report approved in 2024 as part of a review of the Pittsburg Technology Park, in which the city envisioned converting the golf course through zoning changes incorporated into its 2040 general plan.
The data center got the final greenlight in December 2025 when the design review for its first phase of construction was approved by the city.
The project involves the construction of a three-story, 350,000 square foot data center on 22 acres of the 76-acre future technology district. Construction would happen in three phases, with only the first phase approved so far.
Facilities for backup generators, a commercial power yard, and an electrical substation are also planned as part of the project’s Phase I.

Residents criticized the moratorium for allowing the first phase to continue. The city has maintained that the company has the legal ability to move forward, and the city could face a lawsuit if it tried to reverse those decisions.
One public commenter urged the City Council to do just that.
“You approved this, no one even knew what it was,” one resident said. “Our lives as human beings are worth more than any economy, any confidence trick, any AI bubble.”
“You have to get on the phone with the developer and tell them to stop. And take the lawsuit, ok, because our lives are worth more than any kind of lawsuit.”