The City of St. Helena will begin flushing approximately 40 miles of water mains Monday using a zero-discharge process designed to remove debris while filtering and returning water to the system.
The Public Works Department and contractor Hydrologics will begin at the southern end of the city’s water delivery service area and work north, city officials said.
During the week of Oct. 26, crews are scheduled to work between Zinfandel Lane and Chaix Lane/Lewelling Lane.
The week of Nov. 2, work is planned between Chaix Lane/Lewelling Lane and Grayson Avenue/Mills Lane.
During the week of Nov. 9, crews are expected to work between Grayson Avenue/Mills Lane and Pope Street/Mitchell Drive, as well as Allison Avenue and Valley View Street.
The schedule is subject to change, according to the city.
The city will post maps one to two days before work begins in each area and notify affected neighborhoods in advance with door hangers.
Residents are encouraged to temporarily turn off their water or avoid using it while crews work on their street, and after flushing is complete, residents should run an outdoor hose or an unfiltered cold-water tap for two to three minutes, until the water runs clear, before using indoor appliances, the city said.
More information, including updated maps, neighborhood schedules and a video explaining the process, is available at cityofsthelena.gov/zdf.