Monterey Regional Airport is receiving $2.3 million in federal funding for its new passenger terminal.
U.S. Rep. Jimmy Panetta, D-Monterey, announced Tuesday that the Federal Aviation Administration awarded $2,368,257 through its Airport Improvement Program — a grant program that helps fund the planning and development of public-use airports. Panetta’s office said the money will pay for inspections by the terminal’s design team during construction.
“This federal investment will help Monterey Regional Airport move forward with a modern terminal that bolsters safety, efficiency, accessibility, and the passenger experience,” Panetta said.

Monterey Regional Airport is Monterey County’s only commercial service airport. The airport served 659,867 arriving and departing passengers in 2025, up 6.3% from the previous year and the highest annual total in its history.
Airport officials said Monterey serves 11 nonstop markets with an average of 17 departures a day. Those nonstop flights connect Monterey with major hubs and destinations including San Francisco, Los Angeles, San Diego, Seattle, Denver, Dallas-Fort Worth, Phoenix and Las Vegas.
Making way for Taxiway A
The replacement terminal is one piece of the airport’s Metamorphosis Safety Enhancement Program, a federally required series of projects intended to improve safety around the airport’s main commercial runway.
The airport says about 1,850 feet of Taxiway A, which planes use to move around the airfield, needs to be shifted 52.5 feet south to create more space between it and the main commercial runway. The move requires several buildings to be relocated, including the passenger terminal.

Panetta’s office says the new terminal will have 62,754 square feet of public space, five gates and passenger boarding bridges. The broader $200 million-plus Metamorphosis program has also included a new aircraft parking and servicing area, roadway improvements and an added 440-space public parking lot.
Construction on the replacement terminal started on June 6, 2025, according to Monterey Regional Airport. The airport says passengers are expected to begin using this terminal in early summer 2027.
The latest grant follows more than $69 million in federal funding Panetta previously helped secure for modernization and safety improvements at the airport.
Airport Executive Director Chris Morello said the replacement terminal is “more than an airport project,” calling it “an investment in the future of our region.”