A tax on energy companies vying to build in Solano County will appear on the ballot in November following a vote by the county Board of Supervisors this week.
If voters approve the tax, called Measure E, annual fees on commercial wind turbines would go up for the first time since 1994, and new fees for solar projects, battery energy storage systems, natural gas projects and data centers would be established, adding at least an estimated $353,000 in revenue each year to the county’s general fund.
All four supervisors present at Tuesday’s meeting were aligned on the tax, except for Supervisor John Vasquez, who was absent. The vote was 4-1.
“Consider this a backstop,” said Supervisor Mitch Mashburn, who represents District 5, a mostly rural area where a majority of Solano County’s wind turbines and natural gas wells are located.
Supervisors said they want to walk the line between inviting industry and discouraging data centers.
“If they’re going to pillage the county’s resources as they’ve done with water and power and the rest of those things, I want to make sure it’s as expensive as possible for them to do that,” said Mashburn.
Mashburn’s district is also part of the proposed site for a sprawling, billionaire-backed “walkable city” called California Forever, which opponents say will bring with it data centers and other extractive industries.
Currently, the county levies a $0.00003 per kilowatt-hour tax on energy from around 400 commercial wind turbines, generating $56,500 annually for the county’s general fund.
Under Measure E, that rate would go up to $0.00008 per kilowatt-hour for wind and solar projects, $1.50 per megawatt-hour for the battery systems better known as BESS, and $0.30 per thousand cubic feet of energy produced by natural gas wells.
Data centers would cost $5 per square foot for the entire development — significantly higher than the proposed $0.12 per square foot rate that staff proposed to supervisors in June.
Balancing growth and oversight
Most of the roughly 250 data centers in California are 500,000 to 1 million square feet. In the Bay Area, they’re concentrated in Santa Clara County, where officials implemented a tax on data centers that brings in some $4 million a year. Solano County officials estimate that through Measure E, one data center facility could bring in $2 million a year.
Mashburn said that the tax guarantees “at least some miniscule benefit that comes back to our residents to help offset and mitigate all the damage that those plants do to our economy, our air and all those things.”
Vallejo resident Demi Tsasis during public comment at Tuesday’s meeting called for an outright moratorium on data centers, a step cities around California have implemented to buy more time to review proposals.
“Data center developers … look for unregulated markets in financially depressed areas and take advantage,” said Tsasis. “The bees will be gone. Aquifers? Sucked dry. Use of our ag land? Gone. Livestock? Impacted.”

The numerous servers also emit constant sounds, causing hearing damage in many areas, said Tsasis.
Regardless, she said, data centers are unlikely to bring many jobs or income for the county, and tend to lower nearby property values.
“We pull in $80.5 billion in property taxes a year. $3 million is a fraction of that percentage. It has no substantial impact on our ability to run this place.”
For supervisors, a moratorium seems out of the question. In 2024, Solano County supervisors passed a moratorium on BESS development in Solano County after Corby Energy proposed one in Vacaville. BESS are facilities stocked with batteries that store energy for local use.
But the moratorium didn’t matter to the state, said Supervisor Wanda Williams, who represents District 3. Ultimately, the California Energy Commission overrode Solano County’s authority and approved two proposals for BESS sites in Vacaville, largely due to a push by Gov. Gavin Newsom to increase BESS development as part of an effort to reduce the state’s carbon footprint. The two facilities are currently in the planning process.
Williams pointed to other states as examples.
“West Virginia has 250 data centers, and their state stripped them of their ability to have local control,” she said.
A business tax would ensure at least some level of county rule over companies eyeing the vast open spaces around the development of data centers and BESS, said Williams.
Mashburn agreed that a moratorium on data centers is an option. But after what happened with BESS, it wouldn’t make a difference.
“Having a moratorium and having six bucks will get you a whopper as far as the state’s concerned,” he said. “They’re the big bully on the playground that takes our lunch money.”