Plans for a new BART station between Fremont and Warm Springs are progressing after the transit district’s Board of Directors recently passed a resolution in unanimous support of the project’s design phase.

The Feb. 27 vote was 8-0, with Director Bevan Dufty absent, to approve a resolution of public compliance and initial project report as part of its consent calendar for a planned BART station in the Irvington district of Fremont.

The location of the planned Irvington BART station. (Graphic courtesy of city of Fremont)

The decision allows the Bay Area Metropolitan Transportation Commission to vote at a future meeting to allocate $2 million in regional bridge toll funding to complete the station’s design phase. The Alameda County Transportation Commission allocated an initial $16.45 million for the design phase last spring.

The Irvington station was deemed optional when the BART board approved the Warm Springs extension project in 2003. Funding could not immediately be identified for the station’s construction, resulting in service beginning along the Warm Springs extension in 2017 without a stop in the Irvington district.

In 2014, Alameda County voters approved Measure BB, which allocated $120 million toward the station’s construction. Since then, BART officials have worked with the city of Fremont to update the station’s concept plan, surrounding area plan and environmental review.

After significant revisions to the original station plan from 2003, the Fremont City Council approved the station plans last July and the BART board approved the updated environmental review in August.

Final designs for the station are planned for completion by July 2022. If the project remains on schedule, BART will break ground on the station in August 2022, with service expected to begin by August 2026. The entirety of the project is expected to cost roughly $205 million.